Launch Date Announced for August 15, 2027, ETTravelWorld


India is poised to launch its first bullet train on August 15, 2027, according to Union Minister of Railways Ashwini Vaishnaw. This ambitious project, a collaboration with Japan, aims to revolutionize high-speed rail travel in the country, with the initial operational section planned between Surat and Bilimora.

India to Get Its First Bullet Train on Independence Day 2027: Railways Minister Ashwini Vaishnaw

The minister outlined a phased opening of the corridor. Following the Surat to Bilimora segment, Vapi to Surat will become operational. Subsequently, Vapi to Ahmedabad will open, followed by Thane to Ahmedabad, and finally, the full Mumbai to Ahmedabad route.

“The bullet train will be ready in 2027, August 15th, 2027.”

The 508-km Mumbai–Ahmedabad High-Speed Rail Corridor is progressing steadily, with significant construction completed on viaducts, bridges, tunnels, and stations. This corridor is designed to operate at speeds of up to 320 kmph.

The project includes 12 stations, with Sabarmati as the terminal station in Gujarat and BKC as the terminal station in Mumbai. Three depots are under construction. The Mumbai–Ahmedabad High-Speed Rail project passes through Gujarat, Maharashtra, and Dadra and Nagar Haveli.

The high-speed rail line is expected to drastically reduce travel time between Mumbai and Ahmedabad to under two hours. Officials have reported that 320 km of viaduct work is already finished. Land acquisition, tunneling, station construction, and electrification are all advancing concurrently.

India’s high-speed rail project reached a milestone on Friday with the completion of its first mountain tunnel on the Mumbai–Ahmedabad bullet train corridor.

Railway Minister Ashwini Vaishnaw announced that India’s first high-speed rail corridor’s Surat-Bilimora section will open by 2027, with the full Mumbai-Ahmedabad line operational by 2029. The bullet train aims to cover the route in just over two hours, utilizing advanced safety technology. This project is expected to boost regional economies, with plans for four more corridors.

The project integrates Japan’s Shinkansen standards with Indian engineering capabilities. Full corridor operation is anticipated by 2029, with the first operational run targeted for 2027.

In addition to the bullet train, the minister also announced the upcoming launch of the first Vande Bharat sleeper train. Prime Minister Narendra Modi is expected to inaugurate this service in the latter half of January 2026.

“For the bullet train … you can buy a ticket now itself, as it will be operational by 2027,” he further added, jokingly.

  • Published On Jan 2, 2026 at 02:27 PM IST

Join the community of 2M+ industry professionals.

Subscribe to Newsletter to get latest insights & analysis in your inbox.

All about ETTravelWorld industry right on your smartphone!






Source link

24timenews.com

Recent Posts

Morgan Supersport 400 Revealed: Specs, Photos, Details

The Morgan Supersport 400 uses an uprated BMW inline-six engine. It has 402 horsepower and…

8 hours ago

For the first time, scientists pinpoint the brain cells behind depression

Researchers at McGill University and the Douglas Institute have discovered that two distinct types of…

8 hours ago

Should Ford Be Worried About Tesla?

Ford CEO Jim Farley said he’s no longer paying attention to Tesla.   He notes…

18 hours ago

This simple fatty acid could restore failing vision

Changes in eyesight are one of the most common signs of aging. Sit in a…

18 hours ago

IRS officer’s daughter murder: Accused arrested from Delhi’s Dwarka | India News

NEW DELHI: The accused in the murder of an IRS officer's daughter was arrested by…

1 day ago

India to issue tourist visas for Chinese nationals 5 yrs after Galwan clash, ETTravelWorld

More than five years after the Galwan clashes, the Union home ministry has issued revised…

1 day ago